S.NO

DESCRIPTION

Date of Completion

Status

Client, Project Location

        75   

RTR Pipe Installation works SGCP Project, from HDGP to HWGCP 1.New Installation of water line 12” & 14” Threaded Joint for 50 km. Contract Value: 9M

   

     Completed

Abahussain/Saipem    ARAMCO Project, HARADH.KSA

       74

RTR Pipe Installation for SAOMPP project at Well ANDR 743, ANDR 745 and SAOMPP. Installation of water pipeline for 6” Threaded Joint for 14km and 10" Threaded Joint for 8KM . Contract Value 3M

    Ongoing  Nesma and Partner, OMPP Aramco harad, abqaiq
       73

Design and Installation of piping network related to mechanical & Instrumentation work of the Gasoline & Diesel station area at Jafurah Upstream TCF project. Contract Value SAR  1M

   Ongoing

Abdul Mohsen Al Tamimi Co ARAMCO Project, Jafurah.KSA

        72

RTR Piping works BERRI DEVELOPMENT – EXPAND ABU ALICRUDE Processing Facilities & KGP Facilities Expansion. 27000LM Contract Value: SAR 18M

     

Sinopec,ARAMCO Project, Abuali, KSA

71

Maaden Pipeline Maintenance Project (450KM) for 3 years. Maintenance of pumps station, pipe line and inline valves.Contract Value: SAR 18M

30 May 2022 

Completed

Maaden Gold, Taif, KSA

70

GRE/RTR Piping fabrication, installation, hydro testing and re-commissioning.Contract Value: SAR 9M

30 June 2021 

Completed

KCC, HARAD Compressor stations.

69

Marafiq GE 7FA frame unit , auxiliary scopeoverhauling of 28 pumps and motors for 4 units GT21,GT22, GT22 and GT33. Contract Value: SAR 7.7M

19 Dec 2017

Completed

GE, Marafiq IWPP , Jubail

68

Removal & Reinstallation of Waste heat Boiler and Super Heater.

Initial Acceptance 30 Jan 2017

Completed

Raised sulphate acid factory ,Jubail

67

24”water pipe Saudi Aramco Re-Route Pipeline in Ras Tanura of 41 KM to rastanura.Contract Value: SAR 7.7M

 

Completed

Saudi Aramco Re-Route Pipeline in, Ras Tanura CPP

66

Repair and replacement of firewater pipe line and drinking water pipe line near chlorination building of Desalination area. Work include civil , mechanical and piping (RTRP)Contract Value: SAR 14.5M

4 Mar 2018 

Completed

Marafiq IWPP, Plant,Jubail, Client JOMEL

65

Design Engineering & Construction Lump sum for Furnace & Rail foundation Contract Value: SAR 1.1M

 

Completed

NATCO Al-Rushaid Middle East Ltd

64

Constructing the new entrance gate with security room & Access road to Marafiq IWPP Contract Value: SAR 1.5M

 

Completed

JWAP,Jubail

63

HRSG Thermocouple installation testing & Commissioning Contract Value: SAR 190K

 

Completed

JWAP,JUBAIL

62

Fence installation ,HVAC, testing commission Ning, skylight repairing, civil backfilling, compaction, & asphalt work. Contract Value: SAR 1.5M

18-May-18

Completed

KIDMAH LLC KHOBAR

61

GRE/RTR Piping fabrication, installation , hydro testing and recommissioning Contract Value: SAR 8M

Initial Acceptance  

Completed

Fadili gas plant project , KCC/TR

60

TP8 form piping, Pump house, and fire water head installation works. GRE/RTR and FRP

18-Mar-18 

Completed

Pan Gulf industrial Systems, Marafiq Jubail

59

Sprinkler systems installation in 5 plants SWTP9,TP8,nwps, SWC and control room

10-Oct-17

Completed

Pan Gulf industrial Systems, Marafiq Jubail

58

TP9 Pump house construction, civil foundation, Structural works, roof, door and lovers.

10-Apr-18 7

Completed

Pan Gulf industrial Systems, Marafiq Jubail

57

Fire water Upgradation project at Marafiq TP8  including trench preparation, pipe laying, fire hydrants installation  commissioning.GRE/RTR and FRP.Contract Value: SAR 14.8M

2-Feb-16

Completed

Pan Gulf industrial Systems, Marafiq Jubail

56

Steel structural errection work arrond 700 tons in critical area. In addition, grating and light structure.Contract Value: SAR 2.3M

 

Ongoing

KCC, Safco 4 rehabilitation and revamp project

55

Replacement of piping spool works air liquid plant Qurayyah

24-Feb-16

Completed

FS Elloitt, Qurayyah

54

Tank foundation preparation at Sea water cooling area

20-Jan-16

Completed

Pan Gulf industrial Systems, Marafiq Jubail

53

Fire water Upgradation project at Marafiq NWPS including trench preparation, pipe laying, fire hydrants installation  commissioning GRE/RTR and FRP Contract Value: SAR 3.5M

 

Ongoing

Pan Gulf industrial Systems, Marafiq Jubail

52

SEC Scaffolding contract for boiler,hrsg, and steam turbine for major outages (eastern province). Contract Value: SAR 3.5M

 

Ongoing

Saudi Electric Company

51

Relocation of Fire cabinet main control panel, testing and commission   in GTG units

18-Dec-15

Completed

General Electric, Qurayyah CCPP

50

Additional cabling work including testing  from GTE mark Vi panel to Generator Collector Cab Main Control Panel in 18 GTG units. Contract Value: SAR 3.2M

11-Nov-15

Completed

General Electric, Qurayyah CCPP

49

GT#2 painting  and concrete column repair work  including tools  and equipment’s

7-Oct-15

Completed

Atlantic projects, Qurayyah CCPP

48

Scaffolding erection for dismantling and reinstallation of GT#2 pipe rack insulation work

1-Oct-15

Completed

Atlantic projects, Qurayyah CCPP

47

Excavation, reinforcement, preparation and casting of 53 concrete foundation for installation rigging separator, MOVs, pipe support, nitrogen tank, liquid fuel tank etc.Contract Value: SAR 1.8M

20-Sep-15

Completed

KAOFU technical Services, berry gas station, Jubail

46

site facility and Lay down preparation, porta cabin installation, foundation casting, trech preparation for cable laying,

15-Sep-15

Completed

KAOFU technical Services, berry gas station, Jubail

45

Fire water Upgradation project at Marafiq SWTP#9  including trench preparation, pipe laying, fire hydrants installation  commissioning

11-Jul-15

Ongoing

Pan Gulf industrial Systems, Marafiq Jubail

44

PDB relocation, cable tray erection, Cable pulling, Testing and Termination work 

12-Apr-15

Completed

Crown international, Dammam industrial Area

43

 

Cable tray erectrion works

6-Apr-15

 Completed

Aljohran Contracting, SWCC , Alkhobar

42

Maintenance Team for underground piping work  

22-Mar-15

Completed

Maaden Pipe line Project  Taif

47

Modification of Stackor area structural & mechanical work

15-Mar-15

Completed

Eastern province Cement Co.

41

Scaffolding erection for dismantling and reinstallation of Air in let duct filter

3-Mar-15

Completed

Atlantic projects, Qurayyah CCPP

40

Scaffolding erection for dismantling and reinstallation of Bypass stacks,Pipe racks

20-Feb-15

Completed

Atlantic projects, Qurayyah CCPP

38

Scaffolding erection  for gas turbine Major outages

5-Dec-15

Completed

General Electric, PP-3 Power  plant Jeddah

35

HVAC Ducting work at Sabic technology center

5-Aug-14

Completed

Sabic

34

 Construction of Switchgear room

10-Aug-15

Completed

Hyundai Heavy Industries , JSTP Jeddah

33

Installation of sump pump including foundation preparation

7-Aug-15

Completed

Hyundai Heavy Industries , PP_11 Riyadh

32

380KV S/C OHTL inter connection of IRRQAA (#9034 BSP to # 9002 S/S and IRRQAA (#9034) to #9004 S/S

10-Jun-15

Completed

GS Engineering PP12, Riyadh

31

RTRP pipe Line work installation of 18"main header and hydrotesting.

2-May-14

Completed

Maaden Pipe line Project  Taif

30

Scaffolding work for GTE shut down work at Makkah power plant

17-Mar-14

Completed

PP_3 power plant Jeddah

29

33.5KV substation building inside plant civil , HVAC, plumbing and electrical works

15-Mar-15

Completed

Chemnol,Saudi Arabia

28

Scaffolding work for GTE shut down work at Makkah power plat

2-Feb-14

Completed

Makkah Power Plant

27

Fiber Glass reinforce Plastic Butt & wrapping work

15-Jan-14

Completed

Ramoz Al Thumiz Company,RC Jubail

26

 GTG Modification work , collector cab ventilation upgradation project

1-Feb-14

Completed

Saudi Electrical Company, Faras Power Plant Udaliya

25

Installation of sump pump including foundation preparation and preparation and installation of duct bank, Manhole

9-Oct-13

Completed

Hyundai Heavy Industries , PP_11 Riyadh

24

GTG Modification work , collector cab ventilation upgradation project

1-Nov-13

Completed

Saudi Electrical Company,Qurrayah PP1 &2

23

 Fuel gas Buffer Modification project

4-Feb-14

Completed

Hyundai Heavy Industries , PP_11 Riyadh

22

Renovation of old interlock , 50000 Sq feets Removal of old tiles and installation of new tiles

30-Jun-11

Completed

AARTCO. , Royal commission sanitary landsil expansion project.

21

Collector cab modification work for 12 Gas Turbine Generator

18-Oct-12

Completed

General Electric Inc.Marafiq IWPP

20

Repair work for stack welding inside the by stack of Gas Turbine generator

14-Oct-12

Completed

Braden LLC,Marafiq IWPP

19

 Scaffolding Errection for Installing the chiller Air condition unit to Gas turbine generator

2-Aug-12

Completed

Saudi Electrical Company,Qurayyah plant 1& 2,Udaliya

18

 Scaffolding Errection for Installing the chiller Air condition unit to Gas turbine generator

14-Mar-12

Completed

Saudi Electrical Company.

17

Lifting and transportation of  GTG rotor from Faras power to Dammam

12-Feb-12

Completed

General Electric Inc.,Faras Power Plant

16

Performance Heater Valves and pipe line modification on 12 Gas Turbine. Modification of Feed Water lines

30-Jul-12

Completed

General Electric Inc. Marafiq IWPP project

15

Transportation and removal of Transformer from Nasariya power plant to Milsa shop in Dammam for refurbishment

30-Apr-12

Completed

General Electric Inc,Nasariya SEC Plant

14

 

Platform installation on HRSG’

30-May-12

Completed

Doosan heavy industries, Marafiq IWPP

13

Erection of Scaffolding in 3 Stack for repainting of internal stacks. Area around 2500 m3 each up to height 40mts.

30-May-12

Completed

Technical Contracting Company, Al Jubail Power Plant

12

33.5KV substation building inside plant civil , HVAC, plumbing and electrical works and switch gear room

12-Aug-11

Completed

Hyundai Heavy Industries , PP_11 Riyadh

11

Scaffolding project 1 year complete contract for Steam turbine and Gas turbine Generator Inspection and Plant Outages in year 2010 and 2011 , Total 70,000 m3 area erected in different outages and units

17-Jun-11

Completed

General Electric Inc.

10

Site facilities preparation and Site offices(HVAC, Potable cabins and parking facilities installation for Independent Power Plant-11 in Dhurma

30-Jun-11

Completed

Sung Do  IPP-11.Dhurma, Riyadh

9

SCR Probe Access Platforms on 12 Gas Turbines at elevation of 28 Mts height, Access includes ladder, grating, frames and handrails. 2 Sqmts structural Steel platform erected with 100 ton crane

15-Jul-10

 Completed

General Electric Inc. Marafiq IWPP project

8

Renovation of old interlock , 50000 Sq feets Removal of old tiles and installation of new tiles

30-Jun-11

Completed

AARTCO. , Royal commission sanitary landsil expansion project.

7

Cable trench excavation, back filling, asphalt cutting, conducting, cable pooling, fiber optic cable erection work, installing of Security system, fencing work

12-Jun-11

Completed

THALES ,Khursaniyah AFK project,

11

 

380kV Transmission Line from Jubail 380/230 kV SS. To Maaden 380kV Sub Station

30-Jun-08

Completed

Al Masa Group company, Jubail Maaden.

6

Modification of Stack Silencer, removal and installation silencer splitter of 3.1 M from stack of 90M height and welding of supports 20mm think CS plates. 3 Stacks

30-May-11

Completed

Technical Contracting Company, Al-Jubail Power Plant.

5

Iso-phase bus duct pressurization system modification, Installation of tubing’s, relief Valves, intersection drain valves, control panels, solenoid valves, control cabling, commissioning and Testing.  On 12 Gas Turbines and 4 Steam Turbines

15-Dec-11

Completed

General Electric Inc. Marafiq IWPP project

4

Neutral Grounding Transformer repair and replacement of earthing cables and NGT to Bushing box termination and Installation on 4 Steam Turbines

1-Dec-11

Completed

General Electric Inc. Marafiq IWPP project

3

Excitation Cooling Fan power segregation  from Switch Gear room to Excitation compartments 480 V 3 core cable 6KM in 12 Gas turbines and 4 Steam turbines

4-Mar-11

Completed

Jubail O&M Company Marafiq IWPP

2

Fiber Optic Cable Laying and Termination from Mark IV panel to Gas chromatograph panel and Panel installation, commission and Testing.(Modification in Warranty period)

15-Jul-11

Completed

General Electric Inc, Marafiq IWPP Project

1

Civil  and installation work 

21-Mar-11

Completed

Thales Co.